Answer:
It will take 8 hours for the 5 workers to complete the same job.
Explanation:
The amount of work done is the same for both crews.
Work = time * workers
Work = 10 * 4
Work = time * 5
Set the two equal
10 * 4 = time * 5
Divide each side of the equation by 5
10*4/5 = time *5/5
8 = time