A team fixed a road that was 4,800 m long. After working for 30 days, there was still 1,440 m of the road left to fix. On average, how many meters did the team fix per day?
asked
Oct 13, 2019
132k
views
3
votes
A team fixed a road that was 4,800 m long. After working for 30 days, there was still 1,440 m of the road left to fix. On average, how many meters did the team fix per day?
Mathematics
high-school
Eric Fong
asked
by
Eric Fong
7.7k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
The total of the road is 4800 m long. 4800-1440=3360m
We subtract what they have yet to cover from the total to get what they have covered.
So in 30 days they covered 3360 metres.
3660/30 (3660 is divided into 30 equal groups) = 122m
On average they covered 122 metres per day.
Tushar Mate
answered
Oct 19, 2019
by
Tushar Mate
7.6k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.6m
questions
11.2m
answers
Other Questions
How do you can you solve this problem 37 + y = 87; y =
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
i have a field 60m long and 110 wide going to be paved i ordered 660000000cm cubed of cement how thick must the cement be to cover field
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org