a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

2 Answers

4 votes
it will take 4 days to paint the house with 5 men
User Shobhit C
by
8.3k points
6 votes

1 house = 6 men x 5 days = 30 man days

Need 30 man days with only 5 men: 30x = 5 men → x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days