Chandler is setting up a time schedule for beta testing a new software project. Currently, the company has one computer lab compatible with his new program, and there are three other software programs being tested on that lab's systems. Chandler modifies the timeline to account for sharing the computer systems. He is using which schedule analysis tool?

1 Answer

2 votes

Answer: critical chain method

Step-by-step explanation:

Critical chain method is a technique that modifies the project schedule to account for limited resources by addition of duration buffets that are non-work schedule activities to maintain focus on the planned activity durations.