Answer: D- 0.16
Explanation: The Manufacturing cycle efficiency is the percentage of the time spent in producing quality products.
The Manufacturing cycle efficiency (MCE) is calculated thus:
MCE = Process time/ Manufacturing Cycle time(process time + Inspection time+ move time+ Queue time)
MCE= 1.8/(1.8+0.3+2.4+6.8)
MCE=1.8/11.3
MCE= 0.15929
MCE=0.16