Answer:
If cost of capital is 15%
PROJECT X
Year Cashflow DF@15% PV
0 (80,000) 1 (80,000)
1-5 25,000 3.3522 83,805
NPV 3,805
PROJECT Z
Year Cashflow DF@15% PV
0 (120,000) 1 (120,000)
1-4 40,000 2.8550 114,200
NPV (5,800)
Accept project X if the cost of capital is at most 15%
The correct answer is C
Step-by-step explanation:
In this case, the net present value of each project will be computed at 15% cost of capital and the project with positive net present value will be accepted.