Answer:
Machine center A will produce 70 standard bike to maximize his profit
while Machine center B will produce 26 units of deluxe an 2 units of standard
Profit = 1,548
Step-by-step explanation:
luxury bike contribution for constrain resource
18 / 4 = 4.50 dollar of profit per hour
18 / 3 = 6.00 dollar of profit per hour
standard bike contribution for constrain resource
15 / 2 = 7.50 dollar of profit per hour
15 / 3 = 5.00 dollar of profit per hour
Machine center A will produce 70 standard bike to maximize his profit
while Machine center B will produce 26 units of deluxe an 2 units of standard
profit = 70 x 15 + 26 x 18 + 2 x 15 = 1050 + 498 = 1,548