The team has just completed the process of evaluating the success of the data-cleansing project. The team members analyzed how the approach to planning and executing the project worked. They documented how the sponsor and senior management supported the project, as well as the conflicts that were generated by three functional managers. What have they just completed?

User Mbaros
by
7.0k points

1 Answer

5 votes

Answer:

Lessons learned

Explanation:Lessons learned is an activity carried out in project management where the overall problems encountered and steps taken to correct and address those problems are effectively documented and looked into onto to prevent reoccurrence of such problems in future projects and to ensure an improvement in the project performance in the future.

Lessons learned helps project Team/managers to ensure effective and better implementation in forth coming projects.