Zinc Company constructed the following formula for monthly utility cost. Total utility cost = $1,000 + ($5 × Number of labor hours) Assume that 500 labor hours are budgeted for the month of April. Calculate the total utility cost for the month of April. a.$3,500 b.$$6,700 c.$2,200 d.$4,400

1 Answer

3 votes

Answer:

A. $3,500

Step-by-step explanation:

The utility cost for the month of April can be calculated by using the function provided.

Utility cost = $1,000 + ($5 × Number of labor hours)

For April we have 500 budgeted hours,

So using the function the total cost of utility for April is,

Cost = 1000 + (5 * 500) = $3,500