120k views
2 votes
Superior Construction Co. was contracted to plaster all the buildings of a historical preservation project for $2,500,000 over the next 2 years. Total estimated costs to complete are $2,000,000. Actual costs incurred in Years 1 and 2 were $800,000 and $900,000, respectively. Using the percentage-of- completion method, what amount of gross profit would Superior report in Year 1?

A. $225,000
B. $200,000
C. $500,000
D. $250,000

1 Answer

3 votes

Answer:

Gross Profit in Year 1 = $200000

so correct option is B. $200,000

Step-by-step explanation:

given data

historical preservation project = $2,500,000

time = 2 year

estimated costs = $2,000,000

Actual costs Years 1 = $800,000

Actual costs Years 2 = $900,000

to find out

what amount of gross profit would Superior report in Year 1

solution

we find here first Percentage Completion that is express as

Percentage Completion = Cost to date ÷ Estimated Total Cost .............1

put her value we get

Percentage Completion =
(800000)/(2000000)

Percentage Completion = 40%

and

Revenue Recognized will be here

Revenue Recognized = Percentage Completion × Total estimated Revenue ...............2

Revenue Recognized = 40 % × 25000000

Revenue Recognized = 1000,0000

so here Gross Profit in Year 1 will be

Gross Profit in Year 1 = Revenue Recognized - Cost to date of year 1 ..............3

Gross Profit in Year 1 = 1000,0000 - v800000

Gross Profit in Year 1 = $200000

so correct option is B. $200,000

User Ebone
by
5.1k points