Answer:
A) Overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
Step-by-step explanation:
If the project manager uses finish to finish relationships, a successor activity cannot finish until the predecessor activity has not finished.
If the project manager uses start to start relationships, a successor activity cannot start until the predecessor activity has not started.
If the project manager uses start to finish relationships, a successor activity cannot finish until the predecessor activity has not started.