Answer:
A) True
Step-by-step explanation:
Monumental can discharge the contract by frustration. In order for a contract to be discharged by frustration, four conditions have to occur:
- An unforeseeable event must occur: In this case the zoning changes were unforeseeable.
- No party is at fault: the zoning board made the changes to the zoning of the land.
- Performance is impossible: there is no reason why an office building should be built in a residential only area.
- The result is radically different than expected: neither Monumental or Champion Builders expected a zoning change to occur.