For Gundy Company, units to be produced are 5,280 in quarter 1 and 6,400 in quarter 2. It takes 2.0 hours to make a finished unit, and the expected hourly wage rate is $15 per hour. Prepare a direct labor budget by quarters for the 6 months ending June 30, 2020.

1 Answer

0 votes

Answer:

Total cost= $350,400

Step-by-step explanation:

Giving the following information:

For Gundy Company, units to be produced are 5,280 in quarter 1 and 6,400 in quarter 2. It takes 2.0 hours to make a finished unit, and the expected hourly wage rate is $15 per hour.

Quarter 1:

Direct labor cost= 5,280*2= 10,560 hours

Quarter 2:

Direct labor cost= 6,400*2= 12,800 hours

Total cost= (10,560 + 12,800)*15= $350,400