Answer:
a. $ 69 Per Hour of Labor.
b. Total Material Loading Percentage 47.186 %
c. Calculation of Total estimated bill $ 6126.91
Step-by-step explanation:
a) Calculation of rate charged per hour of labor :-
=[ Total Budgeted Costs (Time Charges) / Number of Hours + Profit margin ]
= [ 240900 / 7300 + 36]
= 33 + 36
= $ 69 Per Hour of Labor.
b) Calculation of Material Loading percentage:-
= (40500 + 9950 + 24840) / 414000
= 75290 / 414000
= 0.18186 i.e., 18.186 % (approx)
Total Material Loading Percentage: = 18.186 + 29 = 47.186 %
c) Calculation of Total estimated bill:-
= (69 * 44) + 2100 +(47.186 % of 2100)
= 3036 + 2100 + 990.91 (approx)
= $ 6126.91 (approx)
Conclusion:-
Rate charged per hour of labor $ 69 Per Hour of Labor
Material loading percentage 47.186 %
Total estimated bill $ 6126.91