Answer:
$900,000
Step-by-step explanation:
% completion during the year:
= Actual costs incurred and paid ÷ (Actual costs incurred and paid + Estimated costs to complete)
= $3,000,000 ÷ ($3,000,000 + $6,000,000)
= 33.3333%
Total revenue to be recognized for the year:
= Amount of construction contract × % completion during the year
= $12,000,000 × 33.33333%
= $4,000,000
Actual cost incurred and paid = $3,000,000
Profit for the year:
= Total revenue to be recognized for the year - Actual cost incurred and paid
= $4,000,000 - $3,000,000
= $1,000,000
Accounts receivables at the end of year:
= Billings - Cash Collection
= $3,500,000 - $3,100,000
= $400,000
Cost and profits in excess of billings:
= ($3,000,000 + $1,000,000) - $3,500,000
= $500,000
Total amount of current assets to be recognize at year end:
= Accounts receivables at the end of year + Cost and profits in excess of billings
= $400,000 + $500,000
= $900,000