Answer:
The correct answr is C.
Step-by-step explanation:
Giving the following information:
Cost Machine Hours
January $52,200 20,000
February 75,000 29,000
March 57,000 22,000
April 64,000 24,500
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ highest activity units - Lowest activity units)
Variable cost per unit= (75,000 - 52,200) / (29,000 - 20,000)= 2.53
Fixed costs= Highest activity cost - (Variable cost per unit * HAU)
Fixed costs= 75,000 - (2.53*29,000)= 1600
Fixed costs= LAC - (Variable cost per unit* LAU)
Fixed costs= 52,200 - (2.53*20,000)= 1600