Tile & Grout (T&G) contracts to resurface the insides of the pools at Water World Park. T&G knows that without the resurfacing, Water World will have to delay its seasonal opening. T&G does not perform as promised. As consequential damages, Water World can recover​

A) ​the cost of new pools.
B) ​the difference between T&G's price and the eventual cost of resurfacing.
C) ​the loss of profit from the delayed opening.
D) ​nothing.

User CoursesWeb
by
5.2k points

1 Answer

2 votes

Answer:

C) ​the loss of profit from the delayed opening.

Step-by-step explanation:

As for the information given, Tile & Grout did not perform as they promised.

Since, there is a contract which demands for proper service, and in that contract there is assurance from T&G also to perform well, poor performance will lead to violation of contract.

As there is poor performance it will lead to loss in revenue, of Water World.

Accordingly, water world can demand and has the right to collect, the loss of profit which occurred due to T&G's performance.