Answer:
C) the loss of profit from the delayed opening.
Step-by-step explanation:
As for the information given, Tile & Grout did not perform as they promised.
Since, there is a contract which demands for proper service, and in that contract there is assurance from T&G also to perform well, poor performance will lead to violation of contract.
As there is poor performance it will lead to loss in revenue, of Water World.
Accordingly, water world can demand and has the right to collect, the loss of profit which occurred due to T&G's performance.