Answer:
2.98 minutes per cycle
Step-by-step explanation:
Total work time = 352 minutes per day
Break time = 16 min*3 = 48 min
Lunch time = 60 min
Total time left = 352 - 48 - 60 = 244 min
Demand = 82 jobs a day
Takt time = Total production time available/Demand
Takt time = 244/82
Takt time = 2.9756
Takt time = 2.98 minutes per cycle