161k views
1 vote
The standard quantity of materials for a product was 40 pounds per unit at the standard price of $2.00 per pound. The actual price per pound of materials was $1.50, and the actual quantity used was 44 pounds. An analysis would indicate

User Andre M
by
6.6k points

1 Answer

1 vote

Answer:

It costs $12 less than expected.

Explanation:

Given that,

The standard quantity of materials required for a product are 40 pounds per unit.

Its also known that it costs $2.00 per pound which is the standard price.

So the total amount for the quantity required is $2*40=$80

But here the actual quantity used is 44 pounds per unit.

Also the actualo price is know to be $1.5 ,

hence the actual price would be =$1.5*44=$66

We observe that the actual prize for the quantity required is lesser than the standard price known by $12 .

User Kjarsenal
by
6.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.