Answer:
Estimated manufacturing overhead rate= 141860/4100= $34.6 per direct labor hour
Step-by-step explanation:
Giving the following information:
The predetermined overhead rate uses direct labor-hours.
Direct labor hours:
Basic 2,900
Dominator 1,200
Total= 4100
Manufacturing overhead costs 141,860.
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 141860/4100= $34.6 per direct labor hour