Answer:
Materials handling Allocation= $27.5
Step-by-step explanation:
Giving the following information:
Each chair consists of 10 separate parts totaling $165 direct materials and requires 5.0 hours of machine time to produce.
Materials handling= $2.75 per part
Machining= $5.00 per machine hour
Assembling= $1.50 per part
Packaging= $3.75 per finished unit
Material Handling allocation base is: Number of parts.
Allocation= 10 parts* $2.75= $27.5