My child is in 5th grade ..Please assist with this question..

If 12 boys take 3 days to paint a room,how long will it take 9 boys to complete the same job?

User Temani Afif
by
3.2k points

1 Answer

26 votes
26 votes
it’s a very simple relation 12x 3 = 36 so 9 x ? = 36, so the answer is 4