Answer:
The answer is: the unit variable expense is $1.20 per machine hour
Step-by-step explanation:
In order to calculate the unit variable cost we first take the month with the highest and lowest maintenance expense and machine hours (Highest = month 6, Lowest = month 11). We use the following formula:
unit variable cost = (highest expense - lowest expense) / (highest machine hours - lowest machine hours)
= ($3,680 - $2,780) / (2,440 - 1,690) = $1.20 per machine hour