229k views
2 votes
How long should concrete be allowed to set before it is ready to be used?

7 days
14 days
28 days
35 days

User Lie
by
5.6k points

2 Answers

3 votes
The concrete should be let to set for 28 days
User Dimitar Bonev
by
5.8k points
2 votes

In standard industrial cases, full strength concrete is recognized at 28 days. At seven days, you should have concrete that is cured to 70% full strength or greater. hope this helped!

User Waseem Almoliky
by
5.2k points