Answer:
Manufacturing overhead allocated= $1,260,000
Step-by-step explanation:
Giving the following information:
Scaled Manufacturing estimates annual overhead costs to be $1,200,000 and that 300,000 machine hours will be operated. Using machine hours as a base.
The actual machine hours for the year were 315,000 hours.
We need to find the overhead applied. First, we need to determine the overhead rate.
Overhead rate= total estimated overhead for the period/ total amount of allocation base
Overhead rate= 1200000/300000= $4 per hour
Manufacturing overhead allocated= 315000 hours* 4= $1,260,000