Answer:
Manufacturing overhead cost applied= $280,720
Step-by-step explanation:
Giving the following information:
Plantwide predetermined overhead rate of $23.20 per direct labor-hour.
Estimated $278,400 of total manufacturing overhead cost.
Estimated activity level of 12,000 direct labor-hours.
The company incurred actual total manufacturing overhead costs of $269,000 and 12,100 total direct labor-hours during the period.
Manufacturing overhead cost applied= actual direct labor hours* predetermined overhead rate
Manufacturing overhead cost applied= 12100* 23.20= $280,720