Describe the triple constraint. What are the three components and what is the relationship between them

1 Answer

4 votes

Answer:

The triple constraint represents the three constraints or inputs which control the project's capacity to produce.

The three components are Budget, time, and scope.

The relationship between them is an interdependent or triangular shape.

Explanation:

The triple constraint represents the three constraints or inputs which control the project's capacity to produce. Budget, Scope and Time.

  • Budget - The budget describes the estimated cost of the project.
  • Time: The time represents the deadline to complete the project.
  • Scope: This is simply what needs to be provided.

These 3 components are dependent to each other.

For example, if time is restricted then scope and budget will be affected. similarly.

The relationship between the three is that one of the two other components must decrease while one component increases for the project to succeed as expected.