Answer:
D) Lessons learnt report is the correct option.
Step-by-step explanation:
It is a report performed when a project is concluded. The purpose is to determine and analyze elements of the project which were successful and which were not. They are also known as project post more terms and are aimed at informing process improvements that can mitigate future risks and promote best practices. These reports are considered a key component of effective risk management.