On the seventh day of the iteration, the team realizes that they will not complete 5 of the 13 stories. the product owner says she cannot negotiate the scope of remaining stories any further. What is the team's best course of action?

1 Answer

0 votes

Answer:

First of all the team should excuse to the product owner for not being responsible and committed to the deadline.

Secondly, as they have completed the 8 stories, so they should revise and check the flaws in those stories and send to her.

Because when the product owner will check and happy with them, she will surely discuss the remaining stories with the team.