Answer:
4/5 hour (48 minutes)
Explanation:
Janet works at the rate of ...
(1 job)/(3 hours) = (1/3) job/hour
So, in 1 hour, she has worked 1/3 of the job, leaving 2/3 of the job remaining when Garry shows up.
Garry works at the rate of ...
(1 job)/(2 hours) = 1/2 job/hour
So, together they work at the rate of ...
(1/3 job/hour) + (1/2 job/hour) = (2/6 +3/6) job/hour = 5/6 job/hour
Then the time it takes to do the remaining 2/3 job is ...
(2/3 job)/(5/6 job/hour) = (2/3·6/5) hour = 4/5 hour
It will take 4/5 hour for them to finish the job together.