14 workers, working at the same pace, can lay 36000 bricks in one day. How many workers will be needed to lay 54000 bricks in the same period of time? PlZ And ThanKS
asked
Jul 19, 2020
91.5k
views
4
votes
14 workers, working at the same pace, can lay 36000 bricks in one day. How many workers will be needed to lay 54000 bricks in the same period of time?
PlZ And ThanKS
Mathematics
middle-school
Xaver
asked
by
Xaver
6.6k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
2
Answers
7
votes
Answer: 22 workers
Explanation:
Jeff Hardy
answered
Jul 21, 2020
by
Jeff Hardy
6.8k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
0
votes
Answer: 21 workers
Explanation:
Tyro Hunter
answered
Jul 26, 2020
by
Tyro Hunter
6.8k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
7.2m
questions
9.5m
answers
Other Questions
How do you estimate of 4 5/8 X 1/3
Please solve the following equation. x-6x=56
whats the most accurate estimation of 65+77
Find the additive inverse of 18/23
What is 25% of 500.00
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org