Answer:
The Gross profit/loss recognized for each year under the PC method:
2014 2015 2016
Gross profit(loss) $90 $240 ($630)
Step-by-step explanation:
a) Data and Calculations:
Project's contract price = $3,900
Estimated total cost of the project = $3,000
2014 2015 2016
Costs Incurred To Date $300 $2,400 $4,200
Estimated cost to Complete 2,700 1,600 0
Estimated Total Cost $3,000 $4,000 $4,200
Percentage of completion [PC]= (Costs incurred to date)/(Estimated total cost)
2014 2015 2016
Percentage of completion: $300/$3,000 $2,400/$4,000
Percentage of completion: 10% 60% 30% (100 - 70)
Revenue Allocation: 2014 2015 2016 Total
2014 $390 (10% of $3,900) $390 $390
2015 $2,340 (60% of $3,900) $2,340 $2,340
2016 $1,170 (30% of $3,900) $1,170 $1,170
Total Revenue $3,900
Actual costs incurred ($300) ($2,100) ($1,800) ($4,200)
Gross profit $90 $240 ($630) ($300)