Answer:
the benefit of carrying out the project is $119,666 in today's $
Step-by-step explanation:
initial outlay = -$2,800,000
cash flow 1 = $820,000
cash flow 2 = $820,000
cash flow 3 = $820,000
cash flow 4 = $820,000
cash flow 5 = $820,000
discount rate = 12.5%
NPV = -$2,800,000 + $820,000/1.125 + $820,000/1.125² + $820,000/1.125³ + $820,000/1.125⁴ + $820,000/1.125⁵ = $119,666