Answer:
$3,400
Step-by-step explanation:
The total amount of estimated manufacturing overhead is calculated as;
= Salary of production supervisor + Indirect materials + Rent on factory equipment
Given that;
Salary of production supervisor = $2,000
Indirect materials = $400
Rent on factory equipment = $1,000
Therefore, Estimated manufacturing overhead ;
= $2,000 + $400 + $1,000
= $3,400