Answer:
$317,000 = actual overhead
Step-by-step explanation:
Giving the following information:
Applied overhead= $330,000
Overapplied overhead= $13,000
To calculate the actual overhead, we need to use the following formula:
Under/over applied overhead= real overhead - allocated overhead
-13,000 = real overhead - 330,000
$317,000 = real overhead