Answer: See explanation
Step-by-step explanation:
a. Debit: Raw material $12000
Credit: Account payable $11500
Credit: Material price variance $500
(To record material purchase)
b. Debit: Work in process 11600
Credit: Raw material 11200
Credit: Material price variance 400
(To record material issued)
Note:
Material price variance for (a)= 12000 - 11500 = 500
Work in progress = 5800 × 2 = 11600
Material price variance for (b) = 11600 - 11200 = 400